The following information and photo is from the WW&F Facebook page:
"Engine
9 runs around coach 3 at Alna Center. This is the first time the
locomotive has pulled coach 3. This trip is a result of years of work. A
steam test was done Friday and adjustments were made a good part of
Saturday. #9 moved under her own steam power at 2:45 on Saturday
afternoon and ran well so a short test train was run."
 |
December 4, 2015 |
(SOURCE: WW&F website 11/25/14)
After 5+ years of restoration work, Locomotive #9 reached a critical milestone today – a steam test of the boiler and appliances. While the locomotive is no where near ready – as you can see from the pictures, it’s missing the cab, the tank, and a bunch of other little things – the test was necessary to check for steam leaks. The boiler had undergone several hydro pressure tests in preceding weeks, which helped to eliminate other leaks.